Testing and Start-up of Biogas, Biomethane and Wastewater Treatment Plants.

A team consisting of biologists, engineers, and technicians is involved in the testing and start-up phases of the plant, which undergoes a series of functional tests (mechanical, electrical, pneumatic, chemical).

The testing of the plant includes the following time steps:

Static testing;

Electromechanical testing;

Startup with water or effluent to be treated;

Signing of the acceptance report;

Hydraulic testing;

Start-up with mains water;

Plant acceptance testing;

During the testing and start-up phases, Biowaste’s technical staff supports the operators designated to run the plant for the time necessary for their training.